Cut and fill volumes listed as quantities so you can price them with your own equipment rates.
Questions we get asked
What waste factor do you use on concrete?
5% on a well-prepared slab over compacted gravel with tight forms, 10% on footings, trenches or uneven subgrade. It is always shown as its own line so you can change it, never folded silently into the total.
Do you round to ready-mix increments?
Yes. Ready-mix sells in quarter-yard increments, so the order quantity is rounded up. Short-loading a pour costs far more than the extra concrete.
Do you include rebar laps?
Yes, lap length is added per size. A rebar takeoff without laps under-orders every time.
Bidding more than one job a month?
The retainer covers 4 projects at $650/month, or 10 to 15 at $1,450 with priority 12-hour turnaround. Cancel any time. Most contractors who send a second job switch to it.