Electrical · Medical office fit-out Delivered overnight Published in full, no form

A real electrical takeoff. Every number shown.

Most estimating services gate their samples behind a phone number. This is the whole thing: the quantities, the arithmetic that produced them, every assumption we had to make where the drawings were silent, and the questions we sent back. Check the maths. That is the point of publishing it.

Electrical takeoff, medical office fit-out

Quantities only. No prices invented, you apply your own.
Project 4,800 SF single storey fit-out
Rooms 12
Documents E-1, E-2, E-3, A-1
Revision Permit set

01  Device counts

ItemBasisQty
Duplex receptaclescounted per room off E-2, general purpose68
GFCI receptacleslab, break room, both restrooms, per NEC 210.8(B)7
Single pole switchesone per controlled zone off the lighting plan16
Dimmersexam rooms and offices where the schedule calls for 0-10V11
Recessed canscounted from the fixture schedule, type C137
139 devices total. Counted device by device off the E-sheets, cross-referenced against A-1 for room names. Not scaled, not estimated from area.

02  Branch circuits

ItemCalculationResult
General lighting load4,800 SF x 3.5 VA/SF16,800 VA
Lighting circuits16,800 VA / 277 V = 60.6 A, at 80% of 20 A4 circuits
Receptacle load75 outlets x 180 VA per NEC 220.14(I)13,500 VA
Receptacle circuits13,500 VA / 120 V = 112.5 A, at 80% of 20 A8 circuits
Total branch circuits4 lighting + 8 receptacle12 circuits
The 3.5 VA/SF figure is NEC 2017 Table 220.12 for office occupancy. NEC 2020 revised those unit loads. Which edition your AHJ enforces changes the lighting branch count, so it is raised as RFI 1 rather than assumed silently.

03  Raceway and conductor

ItemCalculationOrder
Home run raceway12 circuits x 85 ft average run1,020 LF
#12 THHN conductor1,020 LF x 3 conductors, plus 10% waste3,366 LF
Device boxesone per device, 4 inch square139
Plaster ringsone per device box139
Panel12 circuits used of 42, 208/120V three phase, 225 A MLO1
Average run length is measured off the plan, not assumed. Spare panel capacity is 30 circuits, 71 percent, which is worth knowing before you bid a job the owner may expand.

04  Assumptions we had to make

Where the drawings were silentWhat we carried
Ceiling type not noted on E-2Accessible lay-in, no fishing allowance carried
Conductor type not specified#12 THHN copper
Wiring method not called outEMT throughout, no MC assumed
Mounting heights not dimensioned18 in AFF receptacles, 44 in AFF switches
Fixture voltage not stated on the schedule277 V lighting, 120 V receptacles
Every one of these is a number that moves if you tell us otherwise. That is why they are listed instead of buried. An estimate without its assumptions written down is not an estimate, it is a guess with a decimal point.

05  RFIs issued back to the contractor

  1. Which NEC edition is the AHJ enforcing?The general lighting unit load for office occupancy differs between the 2017 and 2020 editions of Table 220.12. It changes the lighting branch circuit count and therefore the panel schedule. This is the single largest open variable in this takeoff.
  2. EMT or MC cable?The drawings do not call out a wiring method. The labour difference between EMT and MC on 1,020 LF of home run is larger than the material difference, so we have not chosen for you.
  3. Is the lab receptacle count final?Eight receptacles are shown in the lab with no equipment schedule issued. Lab equipment frequently drives dedicated circuits that are not on the general power plan.
  4. Emergency and egress lighting?No emergency fixtures, no exit signs and no inverter appear on E-2. For a medical occupancy that is unusual. Confirm they are on a separate sheet before you bid this as complete.
  5. Fire alarm scope?Excluded here. If it is in your scope it is a separate takeoff, and it changes the raceway count.
The RFIs are the part that protects you at bid time. A takeoff that raises none has not read the drawings, it has measured them.

06  Excluded from this takeoff

  • Fire alarm and low voltage
  • Data and communications cabling
  • Temporary power
  • Equipment furnished by others
  • Trenching and site work
  • Gear beyond the panel
  • Permits and inspection fees
  • Testing and commissioning
  • Sales tax and freight
  • Overtime and off-hours work
Exclusions are published in plain sight so nothing is assumed covered that is not. The dangerous line item is always the one nobody wrote down.

Send one sheet of your own. We count it free.

Real quantities on your own drawing, back by 8am, no card and no call. If it holds up, the rest of the set is priced by sheet count from $199.